In the MM Purchasing component, a contract is a type of outline purchase agreement against which release orders (releases) can be issued for agreed materials or services as and when required during a certain overall time-frame.
Contracts are of two types:
1. Quantity contracts - Use this type of contract if the total quantity
to be ordered during the validity period of the contract is
known in advance.
2. Value contracts - Use this type of contract if the total value of all release orders issued against the contract is not to exceed a certain predefined value.
But a scheduling agreement is a form of outline purchase agreement under which materials are procured on predetermined dates within a certain time period. A scheduling agreement consists of a number of items, for each of which a procurement type is defined. The
The following are the procurement types:
- Standard
- Subcontracting
- Consignment
- Stock transfer
Delivery of the total quantity of material specified in a scheduling agreement item is spread over a certain period in a delivery schedule, consisting of lines indicating the individual quantities with their corresponding planned delivery dates.
SAP menu to create Contracts and Scheduling Agreement:-
Tips by : Manjunath
SAP Reference Books:
SAP MM, HR, FI, CO, PP, SD, PM,
PS, QM, SM, BW, APO, Basis, ABAP/4, Certification, Books
Back to:
SAP MM (Materials Management)
Configuration Hints and Tips
Return to :-
SAP ABAP/4 Programming, Basis
Administration, Configuration Hints and Tips
(c) www.sap-basis-abap.com All material on this site is
Copyright.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
All product names are trademarks of their respective
companies. The site www.sap-basis-abap.com is in no way affiliated
with SAP AG.
Any unauthorised copying or mirroring is prohibited.