What Is Outline Agreement
Describe what is outline agreement.
Outline agreement are:
1. Contract
2. Scheduling agreement
CONTRACT - ME31K
Contract is a long term purchasing agreement with a vendor concerning
the suppy of materials. These are valid for a certain period of time and
cover a predefined total purchase quantity or value. Here you can't
schedule the lines.
Based on PR and RFQ, you also can create contract.
Create info record before create contract to maintain prices.
Two types of contract
1. Quantity contract
2. Value contract
Prerequisite for contract - T.code ME31K
Enter agreement type - MK quantity contract
Item category - standard
Second screen : enter validiy end
<SAVE> R/3 system generates contract document number XXXXXXX
Create PO against contract.
MIGO against PO
SCHEDULING AGREEMENT - T.code ME31L
Agreement type - LP
Item category - Standard
Create schedule lines - T.code ME38.
Here, do mention the different delivery dates for the material that
are subject for the whole quantity which has been mentioned in the ME31L
SAP MM Reference Books:
SAP
Material Management Interview Questions, Certification and Configuration
Books
Goto:
SAP MM Purchasing
Back to:
SAP MM (Materials Management)
Configuration Hints and Tips
Return to :-
SAP ABAP/4 Programming, Basis
Administration, Configuration Hints and Tips
(c) www.sap-basis-abap.com All material on this site is
Copyright.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
All product names are trademarks of their respective
companies. The site www.sap-basis-abap.com is in no way affiliated
with SAP AG.
Any unauthorised copying or mirroring is prohibited.
|