This setting is done in tcode: SPRO
The path is as follows;
Production - Shop Floor Control - Confirmation
- Define time for confirmation processes.
Here we can determine whether we want to do the
backflushing, goods receipt and cost calculations immediately on confirmation,
as a background process or as an update.
Define Time for Confirmation Processes
- Define control keys that specify when confirmation processes run. You
must specify the order category for the control key (10 PP production order,
20 network, 30 maintenance order, 40 process order).
You can specify the execution time for the following
confirmation processes:
- automatic goods receipt
- backflushing
- determination of actual costs
As execution times the following are available:
- at once online
- at once as an update
- later in the background
The standard settings set is that there are no control profiles. That means that all confirmation processes run online.
Do the following if you want to improve performance
in the area of confirmations.
1. Create a control key.
2. Assign the control key to the desired order
type by entering it in the confirmation parameters for the order type in
the field process control.
3. Make sure that the parallelization type is
defined for the processes that you want to parallelize.
4. Plan the background job for confirmation processes
(Program name: CORUPROC). You can create variants for the individual confirmation
processes.
Tips by : Arvind Khinvesra
Back to:
SAP PP (Production Planning) Configuration
Hints and Tips
Return to :-
SAP ABAP/4 Programming, Basis
Administration, Configuration Hints and Tips
(c) www.sap-basis-abap.com All material on this site is
Copyright.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
All product names are trademarks of their respective
companies. The site www.sap-basis-abap.com is in no way affiliated
with SAP AG.
Any unauthorised copying or mirroring is prohibited.