The Concept (use) of Phantom Assembly
A classic example of phantom assembly is packing
material, they cannot be included in the BOM of the FG but still it is
an assembly that goes with the FG.
Phantom assembly is something that you produce/used
but you cannot count/measure for it, you only can measure for its component.
For example, you are the producer of clip (paper clip) you cannot measure
how much paper clip you already produce, all you know is how much wire
I used to produce clip and how much box of clip, I have produce if you
want to maintain material master for the Clip before it goes to the box,
you can assume that the clip is phantom
A phantom assembly is used when you want to be
able to structure a BOM so it is easy to understand, but don't want to
create too many production orders. Assume an auto Engine. There are
hundreds of components. You might structure them as: Engine block and parts,
camshaft and parts, and 6 piston assemblies. But you don't want to create
3 production orders, too much hassle. So you want to issue the components
for the piston assembly in the same production order as the Engine block.
So you create a new material number for the Piston assembly, but you mark
it as a phantom assembly. That means that when you create the bom for the
Engine assembly, you only have two assemblies, the Engine block and the
Camshaft. You add the phantom assembly for the Piston Assembly to the Engine
block BOM, saying it requires 8 of the phantom assembly. When the production
order is created for the Engine block, the picklist will also include all
of the components of the 8 piston assemblies.
1) When to use, or not use a phantom assembly?
If you need to do cost accounting on how many
hours it takes to assemble a piston assembly, it cannot be a phantom assembly,
because as a part of the Engine block assembly, the labor costs are included
in the Engine block production order, and therefore in the standard cost.
2) Can the assembly people pick out the parts
for the phantom assembly from the all of the components in the Kit?
If the guy assembling the Engine Block gets confused
because of all of the components for the Piston assemblies are there, then
it cannot be a phantom assembly. But if they can seperate them easily,
go for it. A printed circuit board assembly should never be a phantom assembly,
because all of those little parts for each type of PC board must be kept
separate.
3) Do you usually build 100 piston assemblies,
put them into stock, then issue 8 at a time to build an Engine Assembly?
If so, it is not a phantom assembly. If the Piston
assembly is a phantom, you only build the 8 you need while you are building
the Engine Block assembly. You normally do NOT store a piston assembly
(phantom assembly) in stock.
4) However, sometimes a customer calls and wants
you to send them all of the components for One Piston Assembly.
By having it set as a phantom assembly, even
though you don't usually create seperate production orders, in this case
you CAN create a production order for one, pull the components, close the
PO, and send the parts off to your customer.
5) You complete a Engine Assembly.
As you are walking it back to the stockroom,
you drop it on the floor, and it breaks! Damn, but you can still save the
piston assemblies. Since they do have a SAP material number, you CAN put
those back into stock. Most MRP systems WILL recognize that you happen
to have 8 piston assemblies in stock, and will issue those whole assemblies
to the next order for a Engine Block.
In summary:
1. When to use phantom assembly:
a. You want costing to be done but will
not treat that stage as confirmation point.
b. You find that operation is not so important
i.e you do not want analyse the work center output details, etc.
c. You want the operation to be in the
BOM as well as routing, so that product go through that operation.
2. When not to use phantom assembly.
a. If you find that operation is critical
- you cannot treat that as phantom.
b. If you are sending the product to outside
for subcontracting operation.
Tips by : Harneet Toor
SAP PP Reference Books:
SAP Production
Planning , Configuration, Interview Questions and Certification, Books
Back to:
SAP PP (Production Planning) Configuration
Hints and Tips
Return to :-
SAP ABAP/4 Programming, Basis
Administration, Configuration Hints and Tips
(c) www.sap-basis-abap.com All material on this site is
Copyright.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
All product names are trademarks of their respective
companies. The site www.sap-basis-abap.com is in no way affiliated
with SAP AG.
Any unauthorised copying or mirroring is prohibited.
|