No Transaction Code Description
1. CJ20n
Creation of Project
2. CJ20n
Creation of WBS Elements
3. CJ20n
Creation of Activities
4. CJ20n
Assigning relationships to activities
5. CJ20n
Assigning of milestones to activities/WBS Elements
6. CJ20n
Assigning of materials of activities
7. CJ40
Planning of costs to project
8. IMCCP3
Copy Planned cost to budget
9. CJBV
Availability Control of budget
10. CJ30
Assigning Budget to Project
11. CJ20n
Release of Project/WBS Elements/activities
12. CN25
Confirmation of activities
13. CJ20n
Maintain actual dates to milestones of WBS Elements/activities
14. CJ37
Supplement in project
15. CJ38
Return in project
16. KB21n
Direct Activity Allocation
17. CNL1
Create Delivery Information
18. CNL2
Change Delivery Information
19. CNS0
Delivery from project
20. CNL3
Display Delivery Information
21. CJ2c/CJ20N Display
Project
22. CJ41
Display cost planning
23. CJ31
Display Budget
24. CN28
Display Confirmations
25. CJ3B
Display Document (BUDGET)
26. CN29
Cancel/Reverse of Confirmations
27. CN41
Structure Overview
28. CN42N
Overview of Project Definition
29. CN43N
Overview of WBS Elements
30. CN46N
Overview of Networks
31. CN47N
Overview of Activities
32. CN55N
Overview of Sales Document items
33. CN53N
Overview of Milestones
34. CN52N
Components Overview
35. CN42
Enhanced Overview of Project definition
36. CN43
Enhanced Overview of WBS Elements
37. CN44
Enhanced Overview of Planned Orders
38. CN45
Enhanced Overview of Orders
39. CN46
Enhanced Overview of Networks
40. CN47
Enhanced Overview of Activities
41. CN48
Enhanced Overview of Confirmations
42. CN52
Enhanced Overview of Components
43. CN53
Enhanced Overview of Milestones
44. CNS54
Enhanced Overview of Sales and Distribution Documents
45. CNS55
Enhanced Overview of Sales Document items
46. ME5J
Purchase requisitions for Project
47. ME2J
Purchase Orders for Project
48. CNMM
Project Oriented Procurement
49. CN60
Display change documents
50. S_ALR_87013542 Actual/Commitment/Total/Plan in Control Area Currency
51. S_ALR_87013557 Budget/Actual/Variance
52. S_ALR_87013560 Budget Updates
53. S_ALR_87013532 Plan/Actual/Variance
54. S_ALR_87013533 Plan/Actual/Commitment/Rem.Plan/Assigned
55. S_ALR_87013534 Plan1/Plan2/Act/Commitment
SAP PS Reference Books:
SAP Project
System, Interview Questions and Certification, Books
Back to SAP PS Main Menu:
SAP PS (Project System) Hints
and Tips
Return to :-
SAP ABAP/4 Programming, Basis
Administration, Configuration Hints and Tips
(c) www.sap-basis-abap.com All material on this site is
Copyright.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
All product names are trademarks of their respective
companies. The site www.sap-basis-abap.com is in no way affiliated
with SAP AG.
Any unauthorised copying or mirroring is prohibited.
|