First, you will need to set up the planning calendar.
Menu path: Production -> MRP -> Master Data -> Planning Calendar (MD25)
You will then need to use this planning calendar (the one you created) in the material master when planning your raw materials (MRP2 View in 4.6C - Field name : Planning Calendar).
1. When you maintain the planning calendar you will need to enter a valid from date and valid to date.
2. Your periods will also need to be set up and they will be weekly,
for example:
From Date :
11/23/2001 To Date :
11/29/2001 (11/23 is a Friday, this is your from date).
Do this for as may weeks as you wish (say weekly
for 2 years).
3. When you have set up the planning calendar, you will then need to
make some changes to the weekly lot size configuration
(WB), or you may need to create a new lot size key
if you do not want to change 'WB'. Essentially, you will need to use the
following in the lot size configuration (OMI4)
:
No. of Periods : 1
LotSizeProced.: P
LotSize ind : K
Scheduling : 1
By using the above, you are connecting the planning calendar to your lot size key.
Return to :-
SAP ABAP/4 Programming, Basis Administration,
Configuration Hints and Tips
(c) www.sap-basis-abap.com All material on this site is
Copyright.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
All product names are trademarks of their respective
companies. The site www.sap-basis-abap.com is in no way affiliated
with SAP AG.
Any unauthorised copying or mirroring is prohibited.