Sappers:
Is there a status that can be set for a network activity that will stop time confirmations from being processed? TECO stops changes to the basic data, but allows further time confirmations.
TIA
Reply : Subject : PS Network Status's & Confirmations
hi...
you can lock account assignment for the network/activity
in consideration depending on whether the network is header/activity
assigned. This disallows the confirmation of
the activities.
...else you can use the user status
regards...